Project plan per the milestones described at Here

 

MilestonesTimepointStatus
(MS0) Open Intent to Participate

10/2/17

 

Done

(MS1) Planning complete (scenarios or deliverables defined)                   

        scenarios that Daisy4NFV will support in Fraser:

            os-nosdn-nofeature-ha

os-odl-nofeature-ha

11/3/17

 

Done
(MS2) Detailed test case descriptions communicated to test project teams11/17/17 

(MS3) Installer integration with OpenStack completed

try to implement DPDK scenario in this phrase.

2/2/18 

(MS4) Infrastructure updates completed              

1/12/18

 

 

(MS5) Scenario integration and Feature Freeze completed.  

huzhj: All required component required by all scenarios shall be integrated and workable.

3/2/18 

 

(MS6) Test cases implemented, preliminary documentation completed,

      and stable branch open                                                 

        Preliminary documentation:

            Installation Guide

3/16/18 

 

 
(MS7) Stable branch window close

4/6/18   

 
(MS8) Formal test execution completed

4/17/18

 
(MS9) JIRA issues assigned to release closed or deferred4/18/18 

(MS10) Documentation completed                                               

        User manual

        Installation Guide

        Rlease Notes

4/19/18 
(MS11) Release 6.04/20/18 

(MS12) Release 6.1

5/25/18 
(MS13) Release 6.26/29/18 
   