Name | |
Project name | Barometer |
Milestones affected | MS5 |
Rescheduled or exempted? | Rescheduled |
Other projects affected | APEX |
Background description | A change in the APEX installer requirements caused integration to take much longer to implement than expected. We have also been blocked on getting the required materials into RDO. |
Schedule impact | I believe that MS5 will be pushed out a month in order to get the remaining pieces into RDO. MS6 should not be affected as Barometer feature development is independent of APEX integration.
|
Recovery plan | The recovery plan is to work closer with RDO to get the necessary changes approved. |
Milestone schedule change | MS5: September 21st, 2018 |
Risk | The main risk is RDO acceptance of the proposed patches. However, most of the preliminary patches have been accepted which is a good sign that all will be accepted. |
Status | |
Decision | |
2 Comments
Tapio Tallgren
Looks good to me
Trinath Somanchi
Good to go.