Name

Project name

Barometer
Milestones affectedMS5
Rescheduled or exempted?Rescheduled
Other projects affectedAPEX
Background descriptionA change in the APEX installer requirements caused integration to take much longer to implement than expected. We have also been blocked on getting the required materials into RDO.
Schedule impactI believe that MS5 will be pushed out a month in order to get the remaining pieces into RDO. MS6 should not be affected as Barometer feature development is independent of APEX integration.


Recovery plan

The recovery plan is to work closer with RDO to get the necessary changes approved.

Milestone schedule changeMS5: September 21st, 2018
RiskThe main risk is RDO acceptance of the proposed patches. However, most of the preliminary patches have been accepted which is a good sign that all will be accepted.
Status
Decision