Name@ shangxdy

Project name

Parser
Milestones affectedM2,M3,M4
Rescheduled or exempted?Rescheduled
Other projects affectedN/A
Background descriptionBIS deny order from USA
Schedule impactMS2, MS3
Recovery plan

Not sure, but we will be back to community as long as the deny order is solved.

Milestone schedule changeMS2, MS3 align to MS4 (7/13/18)
Risk

We have to move Parser out of Gambia release if the deny order still exists in MS5 or MS6.

StatusWithdrawn
DecisionN/A