For the C release, the HA project will include the following work

1, High Availability Deployment Guideline for OPNFV

JIRA No. HA-21

Plan to finish the documentation work before July

No dependancy on other projects

2, Gap Analysis of High Availability for OpenStack

JIRA NO. HA-23

Plan to finish the documentation work before July

No dependancy on other projects

3, High Availability testing

JIRA NO. HA-24

Plan to finish the testing before August

Depend on Yardstick team for the test tooling development.