1. Project name
Bottlenecks

2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues
Green

3.Name of person providing status
Hongbo Tian

4.a link to your Jira tasks (filtered on R2) https://jira.opnfv.org/browse/BOTTLENECK-20?jql=project%20%3D%20BOTTLENECK%20AND%20labels%20%3D%20R2

5.a link to your Jira dashboard https://jira.opnfv.org/browse/BOTTLENECK/?selectedTab=com.atlassian.jira.jira-projects-plugin:issues-panel

6.a statement of your progress at linking cross project dependencies in Jira
Bottlenecks is dependent on CI?since one of our committers is the committer of CI. He is working on cooperation between bottlenecks and CI and almost finished most work?

7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile)
We have identified Jira tasks and developed the codes for bottlenecks. And
We have upload some codes into gerrit.

8.a statement of your readiness (high level planning complete & in Jira) for future sprints
We are planning 3 Sprints:
Sprint 1: bottlenecks framwork and test cases design(finished)
Sprint 2: test tools and first testcase coding(ongoing), since the testcase can cover many scenarios, it will take days for coding.
Sprint 3: system bottlenecks analysis and first test case scalability. Bottlenecks documents

9.a statement about any issues you have
None yet

10.how & when you will finish getting your tasks & dependencies into Jira if not complete
Jira is complete for Sprint 1 and 2. Design has been finished and we are working on coding.

11.how and when you will get ready to start development for Brahmaputra if not ready now
We are coding for bottlenecks.

12.a statement summarizing your project risk analysis & planning status
Low risk and on track so far.