1. Project name
DPACC

2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues
Green

3.Name of person providing status
Lingli Deng

4.a link to your Jira tasks (filtered on R2) https://jira.opnfv.org/browse/DPACC-6?jql=project%20%3D%20DPACC%20AND%20labels%20%3D%20R2

5.a link to your Jira dashboard https://jira.opnfv.org/browse/DPACC/?selectedTab=com.atlassian.jira.jira-projects-plugin:issues-panel

6.a statement of your progress at linking cross project dependencies in Jira
None dependency to other projects is identified yet.

7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile)
We have agreed on the scope and structure and solicited various input for the 5 work items of C release.

8.a statement of your readiness (high level planning complete & in Jira) for future sprints
We are planning 3 Sprints:
Sprint 1: July, DPACC Framework
Sprint 2: July, DPACC usecases
Sprint 3: July, Gap analysis for OpenStack for DPACC
Sprint 4: July, DPACC API Guidelines
Sprint 5: July, DPACC High Level Requirements 

9.a statement about any issues you have
None yet

10.how & when you will finish getting your tasks & dependencies into Jira if not complete
Jira is complete.

11.how and when you will get ready to start development for Colorado if not ready now
The work items are already started and in progress.

12.a statement summarizing your project risk analysis & planning status
Low risk and on track so far.