MilestonesTimepointStatus
(MS0) Open Intent to Participate

3/27/17

 

Done

(MS1) Planning complete (scenarios or deliverables defined)                   

        scenarios that Daisy4NFV will support in Euphrates:

            os-nosdn-nofeature-ha (Who is the owner of this Scenario?)

5/2/17

 

Done
(MS2) Detailed test case descriptions communicated to test project teams5/22/17 
(MS3) Installer integration with OpenStack completed5/30/17 

(MS4) Infrastructure updates completed                                        

       Make         huzhj:Make sure our B/M V/M PODs are all qualified to be Production CI POD in Euphrates release.

6/5/17

 

 

(MS5) Scenario integration and Feature Freeze completed   

huzhj: All required component required by all scenarios shall be integrated and workable.

7/21/17    

 

(MS6) Test cases implemented, preliminary documentation completed,

      and stable branch open                                                 

        Preliminary documentation:

            Installation Guide

8/11/17 

 

 
(MS7) Stable branch window close

9/1/17   

 
(MS8) Formal test execution completed

9/18/17

 
(MS9) JIRA issues assigned to release closed or deferred9/20/17 

(MS10) Documentation completed                                               

        User manual

        Installation Guide

        Rlease Notes

9/22/17 
(MS11) Release Euphrates 5.09/25/17 

(MS12) Release Euphrates 5.1

11/2/17 
(MS13) Release Euphrates 5.212/13/17