Name | Tim Rozet |
Project name | Apex |
Milestones affected | M3 |
Rescheduled or exempted? | Rescheduled to 6/22 |
Other projects affected | None |
Background description | Gambia Apex deployments are working in virtual environment, but not on baremetal. Looks to be some issue with Ceph. |
Schedule impact | Since virtual environments work, there should be no impact on other projects to integrate with Apex. This delay should not propagate to other milestones.
|
Recovery plan | Going to investigate today what the Ceph problem is. There should be no other issues after that one is fixed. |
Milestone schedule change | 6/22 |
Risk | Low risk |
Status | |
Decision | |