Page properties


Name

Project name

Calipso
Milestones affectedMS5, MS6
Rescheduled or exempted?Rescheduled
Other projects affectedNone
Background descriptionChanges to Apex installer requires additional actions to complete integration
Schedule impactWe should catch up so that no other milestones are missed.
No additional change is needed for MS6 as compared to previous releases, so MS5 and MS6
are expected to be met at the same time
Recovery plan

Ilia Abashin and Koren Lev are working to fix the Apex installer
integration and catch up with the schedule. Tim Rozet and David McBride are helping
to minimize the delay.

Milestone schedule changeMS5, MS6: September 16th, 2018
RiskSince we're not dealing with a unique issue, the risk should be minimal
Status
Decision