1. Project name
Dpacc DPACC

2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues
Green

...

7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile)
We have agreed on the scope and structure and solicited various input for the 4 5 work items of R2C release.

8.a statement of your readiness (high level planning complete & in Jira) for future sprints
We are planning 3 Sprints:
Sprint 1: OctoberJuly, Dpacc DPACC Framework
Sprint 2: NovemberJuly, Dpacc DPACC usecases
Sprint 3: DecemberJuly, Dpacc gap analysis and test specificationGap analysis for OpenStack for DPACC
Sprint 4: July, DPACC API Guidelines
Sprint 5: July, DPACC High Level Requirements 

9.a statement about any issues you have
None yet

...

11.how and when you will get ready to start development for Brahmaputra Colorado if not ready now
The work items are already started and in progress.

...