This page shows planned work for Moon.

Euphrates

Deliverables:

  • Deployment support throught multiple POD with Master-Slave mode
  • Upstream to OpenDaylight and OpenStack
  • Multi-POD bottlenect test use case

Project plan per the milestones

MilestoneStatus/PlanNotes
(MS0) Open Intent to Participate4/16/17: Done 
(MS1) Planning complete (scenarios or deliverables defined)5/2/17: Done
See "Deliverables" above.
(MS2) Detailed test case descriptions communicated to test project teams5/22/17 
(MS3) Installer integration with OpenStack completed5/30/17 
(MS4) Infrastructure updates completed6/5/17 
(MS5) Scenario integration and Feature Freeze completed7/21/17 
(MS6) Test cases implemented, preliminary documentation completed, and stable branch open8/11/17 
(MS7) Stable branch window close9/1/17 
(MS8) Formal test execution completed9/18/17 
(MS9) JIRA issues assigned to release closed or deferred9/20/17 
(MS10) Documentation completed9/22/17 
(MS11) Release Danube 1.0
9/25/17 
(MS12) Release Danube 2.0
11/2/17: N/A
 
(MS13) Release Danube 3.012/13/17: N/A 

 

Danube

Deliverables:

  • Deployment support via a second installer (beside Compass4NFV)
  • Graphic interface development
  • Multi-POD bottlenect test use cases.

...